Levin JCC Progress Report #3 July 16, 2010
Levin JCC Progress Report #3 July 16, 2010
Progress continues as the clearing and rough grading of the site gives way to preparation of the building pad. The corners of the building are marked, with the pool and pool structures located at the rear of the site. Discussion with vendors is continuing on final details and pricing of the pool and equipment for security, food service, audio-visual needs, phones and data. Finishes have been studied and discussed, and the architect will make final recommendations.
Progress continues as the clearing and rough grading of the site gives way to preparation of the building pad. The corners of the building are marked, with the pool and pool structures located at the rear of the site. Discussion with vendors is continuing on final details and pricing of the pool and equipment for security, food service, audio-visual needs, phones and data. Finishes have been studied and discussed, and the architect will make final recommendations.
| Two-Week Forecast: 7/17/10 – 7/24/10 |
|