Levin JCC Progress Report #3 July 16, 2010

July 16, 2010
by

Levin JCC Progress Report #3 July 16, 2010

Progress continues as the clearing and rough grading of the site gives way to preparation of the building pad.  The corners of the building are marked, with the pool and pool structures located at the rear of the site.  Discussion with vendors is continuing on final details and pricing of the pool and equipment for security, food service, audio-visual needs, phones and data.  Finishes have been studied and discussed, and the architect will make final recommendations.

Progress continues as the clearing and rough grading of the site gives way to preparation of the building pad.  The corners of the building are marked, with the pool and pool structures located at the rear of the site.  Discussion with vendors is continuing on final details and pricing of the pool and equipment for security, food service, audio-visual needs, phones and data.  Finishes have been studied and discussed, and the architect will make final recommendations.

Two-Week Forecast:  7/17/10 – 7/24/10
  • 7/19:  Foundation work to begin and continue 2-3 weeks
  • 7/19:  Receive pricing of Pool Buildings
  • 7/21:  Final selection of finishes (tentative)
  • 7/23:  Receive final pricing of pool
Advertisement
No comments yet

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Connecting to %s

Follow

Get every new post delivered to your Inbox.