Levin JCC Progress Report #2 July 2, 2010

July 1, 2010
by

Levin JCC Progress Report #2 July 2, 2010

We are seeing a lot of progress on the jobsite now.  As the photos below show, the clearing is complete and the trucks are in motion.  Grading has begun, and the preliminary layout of the pool, playing field and building pad are becoming clear.   Our construction trailer is on-site, albeit without utilities (anticipate getting power any day).  The pool documents are 95% complete and the plans for the auxiliary pool buildings have been submitted for permit and pricing.  We are finalizing the scope of telecom, security and AV subcontracts and beginning selection of the giant slide and furniture.  A lot can happen in two weeks!!

Two-Week Forecast:  7/3/10 – 7/16/10
  • 7/5:  Removal of stumps & debris complete
  • 7/6:  JF submits final scope of telecom/security/AV needs
  • 7/7:  Final selection of finishes
  • 7/9:  Building pad grading complete
  • 7/9:  Pool buildings pricing due

Building Pad in the Works

Playing Field

Construction Entrance

One truck load at a time

Advertisement
No comments yet

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Connecting to %s

Follow

Get every new post delivered to your Inbox.