Levin JCC Progress Report #2 July 2, 2010
Levin JCC Progress Report #2 July 2, 2010
We are seeing a lot of progress on the jobsite now. As the photos below show, the clearing is complete and the trucks are in motion. Grading has begun, and the preliminary layout of the pool, playing field and building pad are becoming clear. Our construction trailer is on-site, albeit without utilities (anticipate getting power any day). The pool documents are 95% complete and the plans for the auxiliary pool buildings have been submitted for permit and pricing. We are finalizing the scope of telecom, security and AV subcontracts and beginning selection of the giant slide and furniture. A lot can happen in two weeks!!
| Two-Week Forecast: 7/3/10 – 7/16/10 |
|
Building Pad in the Works
Playing Field
Construction Entrance
One truck load at a time